In dezember 2007 in sand reclamation line was assambled new 75m3 hooper, with capacity 130 tonnes.
In july 2007 starts to work furnace INDUCTOTERM-ELPHIAC with 2 melting-pots with capacity of 2000 kg each, frequency - 500 Hz, with temperature till 1750 °C. Performance 2.1T/h
In november 2006 was finished assembly of sand mixer and reclamation plant for furan resin bonded sand.
Furan resin bonded sand is knocked out and regenerated in the reclamation plant with output rate of 6T/h, in which mechanical regeneration (shakeout and vibratory sand processor) and regeneration in fluidised bed coller/classifier is made
Serial and not serial forming of biggest castings is made by high-speed continuous sand mixer OMEGA SPARTAN II 220AB with output rate 20T/h using furan resin bonded sand process
On April 15, 2012 there will be started one of the most modern lines in Europe to form in masses of self-hardening castings with increased technical requirements and complex spatial shape by IMF...
Project “Implementation of the Foundry Magnus-Nord FAST LOOP modern system for the production of castings with higher technical requirements and intricate spatial shape” is financed by the European...